This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
Our builders are making good progress against our Ofgem deadline for installing and commissioning the air source heat pumps – this week saw them lay
Suddenly it feels like we’ve progressed from having an old cow shed with new walls and ceilings into it becoming a proper building – with
After all the terrible weather we’ve been having this summer (the past week being no exception) it looks like we’re finally getting some sun! It’s
We fully intended to decide our heating and power solutions early on (in fact we started getting quotes around Christmas) but somehow everything else seemed to