This week had a tense start – Tuesday was our deadline for getting all three air source heat pumps installed and commissioned. The two for
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This week had a tense start – Tuesday was our deadline for getting all three air source heat pumps installed and commissioned. The two for
With our builders on their Christmas break, it’s been feeling very quiet around here, especially when family and friends went home after staying for Christmas
We entered our 8th month of building work this week- and what a week of progress! The windows and french doors were installed in the
It’s been a pretty stressful week with so much to do at home and a busy few weeks at work, so this weekend it felt
Last week we talked about the progress our builders have made on the top floor of the farmhouse, insulating the space and building up the
This has been an incredibly busy week, despite the rain (so much for summer). Progress in the farmhouse has been impressive – our builders came