This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
Our builders are making good progress against our Ofgem deadline for installing and commissioning the air source heat pumps – this week saw them lay
Our builders finished for Christmas on Thursday afternoon, but not before yet another productive week. They’ve mostly been getting on with indoor jobs, now working
This week started so well. National Grid arrived on Monday – having been booked for at least 4 months – and got on installing new
The end of the shippon that will become our new home seems to be coming along nicely. The carpenters have been working hard and have
This was the week our builders started replacing the rotten bathroom & ensuite roof on the farmhouse. We hadn’t expected to have to do this,