This week had a tense start – Tuesday was our deadline for getting all three air source heat pumps installed and commissioned. The two for
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This week had a tense start – Tuesday was our deadline for getting all three air source heat pumps installed and commissioned. The two for
This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
With deadlines looming, we’ve taken every opportunity we could to get out into the shippon and carry on painting our new house. A date for
With our builders on their Christmas break, it’s been feeling very quiet around here, especially when family and friends went home after staying for Christmas
This week didn’t start as well as it could have done. We woke on Monday to find our main new drain cover had blocked overnight,
This week we started to prime the top floor of the farmhouse. The plasterers finished at the end of last week and we’ve been allowing