This feels like another mini-milestone week. It was our site manager Paul’s final week on site – even though there are bits to finish, these
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This feels like another mini-milestone week. It was our site manager Paul’s final week on site – even though there are bits to finish, these
An exciting moment this week when our external stairs were installed up to the games room! We chose steel stairs over wooden ones because we
Sitting outside at the end of the bank holiday, it’s hard to remember how the week started. We’ve been pretty lucky with the weather over
This has been a busy week all round. It’s also been a messy week for our site manager. Our farmhouse septic tank needed upgrading well
This week had a tense start – Tuesday was our deadline for getting all three air source heat pumps installed and commissioned. The two for
This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase