We’ve managed to find time to make more progress in the games room in the New Barn this week. The pool table we ordered arrived
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
We’ve managed to find time to make more progress in the games room in the New Barn this week. The pool table we ordered arrived
This week marked the completion of our building contract, which means we are officially out of Stage Five (the construction stage) of the first phase
This has been our first week without builders on site since February 2023 (other than Christmas) and it’s felt extraordinarily quiet around the place. Having
Evening jobs and the long weekend means we’ve managed to make a bit more progress than normal. The two laundries are taking shape after we
A week of beautiful weather resulted in a significant amount of progress. The week started with the plasterers finishing the rendering on the front of
Two more tasks this week and now all of our buildings are now weathertight. The garage and laundry were both missing doors but as our