We made more fit-out progress this week. In the garage and laundry rooms the concrete floor was poured, and will be sanded down once it’s
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
We made more fit-out progress this week. In the garage and laundry rooms the concrete floor was poured, and will be sanded down once it’s
This week had a tense start – Tuesday was our deadline for getting all three air source heat pumps installed and commissioned. The two for
The weeks have finally started to blend into each other, and it’s getting hard to remember how far our builders had got last weekend, and
It seems like we have slow weeks and busy weeks at the moment! We’ve managed to make a bit more progress this week – both in