This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase
Our builders are making good progress against our Ofgem deadline for installing and commissioning the air source heat pumps – this week saw them lay
It’s been a particularly busy week on site, with the ‘first fix’ stage starting in in our new house. Almost all the walls have been
This was the week our builders started replacing the rotten bathroom & ensuite roof on the farmhouse. We hadn’t expected to have to do this,