This has been a busy week all round. It’s also been a messy week for our site manager. Our farmhouse septic tank needed upgrading well
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This has been a busy week all round. It’s also been a messy week for our site manager. Our farmhouse septic tank needed upgrading well
We made more fit-out progress this week. In the garage and laundry rooms the concrete floor was poured, and will be sanded down once it’s
Another big job ticked off this week – the plasterers tackled the upstairs room of the communal building. It’s a fairly large room, half with
On one hand, when you start to talk about carpets you think you’re nearly at the end of the build. But then you look outside
We have flooring in our new house! It was due to go down a couple of weeks ago but the wet weather meant the house
This week was the first anniversary since we properly started the building work – it was supposed to take 8 months for the first phase