This feels like another mini-milestone week. It was our site manager Paul’s final week on site – even though there are bits to finish, these
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
This feels like another mini-milestone week. It was our site manager Paul’s final week on site – even though there are bits to finish, these
It definitely feels like we’re coming to the end of the build phase now – with most of our jobs being finishing touches outside.It’s mainly
This has been our first week without builders on site since February 2023 (other than Christmas) and it’s felt extraordinarily quiet around the place. Having
An exciting moment this week when our external stairs were installed up to the games room! We chose steel stairs over wooden ones because we
A week of beautiful weather resulted in a significant amount of progress. The week started with the plasterers finishing the rendering on the front of
Two more tasks this week and now all of our buildings are now weathertight. The garage and laundry were both missing doors but as our