We set aside this weekend to continue work on a project that’s likely to be the longest-running project that we’ll do ourselves – replacing the gravel in the kitchen garden with reclaimed
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
We set aside this weekend to continue work on a project that’s likely to be the longest-running project that we’ll do ourselves – replacing the gravel in the kitchen garden with reclaimed
Let’s start this week’s blog with progress in the Cow Shed. Our tiler Jonas has been busy in the ensuite, finishing the back wall (more complicated than it sounds since every tile has
Our builders have made good progress in the Cow Shed this week, putting the final wall boards in the ensuite and installing the cistern. The thing that has
Work has continued this week in our one bed cottage. All the insulation is now in and our carpenter has started putting in the stud wall between the bathroom, bedroom and kitchen. The plumbers
Unsurprisingly, this has been another non-stop week – a very productive one though. Our main goal was to get the remaining bedrooms and ensuite cleaned
This has been our first week without builders on site since February 2023 (other than Christmas) and it’s felt extraordinarily quiet around the place. Having