Another week, and more progress across the site. One of the most exciting for us is the air source heat pumps being installed for our
Renovating beautiful self-catering holiday cottages in the Blackdown Hills in East Devon
Another week, and more progress across the site. One of the most exciting for us is the air source heat pumps being installed for our
With deadlines looming, we’ve taken every opportunity we could to get out into the shippon and carry on painting our new house. A date for
With our builders on their Christmas break, it’s been feeling very quiet around here, especially when family and friends went home after staying for Christmas
Roofs seem to have been the focus for this week. Our builders completed the new rafters along the front of the shippon – now these
Most of the focus this week has been on starting the foundations for our ancillary garage/laundry building. Having removed the walls and cleared the rubble
We haven’t really talked about our third barn much so far – the main reason being that it’s almost completely derelict. The roof was taken